What are the ground trial installation requirements for coal mining scraper conveyor,Listed below for everyone.
(1) The head of the coal mining scraper conveyor must be placed correctly, and the stable pad is not shaken;
(2) The laying of the chute in the middle of the coal mining scraper conveyor must be flat, stable and straight, and the laying direction must be correct, that is, the plank of each section must be facing the machine head;
(3) The coal baffle plate and the groove gang must be tight, tight and seamless;
(4) Scraper conveyor with shovel coal plate, the shovel coal plate and the groove gang must be close, tight and seamless;
(5) The welding ring of the circular chain of the coal mining scraper conveyor must not face the middle plate and must not be tightened; the number of links in each section between the double-chain scrapers must be equal. The direction of the scraper must not be wrong. The head of the bolt connected to the scraper in the horizontal direction must be in the direction of operation; the head of the bolt connected to the scraper in the vertical direction must be facing the middle plate;